What an ESOS action plan is
An ESOS action plan is a forward-looking statement of the energy-efficiency measures a participant intends to implement, following its ESOS energy audit.
The requirement sits in regulation 34A of the Energy Savings Opportunity Scheme Regulations 2014 (SI 2014/1643), inserted by the ESOS (Amendment) Regulations 2023 (SI 2023/1182).
The action plan converts audit recommendations into commitments.
It states which energy-saving measures the organisation intends to take, and it is followed by annual progress updates reporting delivery against those commitments under regulation 34B (Part 6A, SI 2023/1182).
The detailed requirements are set out in Sections 12–13 of the GOV.UK full ESOS guidance.
Unlike the audit itself, the action plan and its progress updates are published — creating public accountability for the commitments made.
Who must submit an action plan
Every participant that was required to notify compliance for the third compliance period — Phase 3, notification deadline 5 June 2024 — had to submit an action plan.
If your organisation was in scope for Phase 3, the action plan obligation followed automatically.
The test for being an ESOS participant is the "large undertaking" definition: 250 or more UK employees, or annual turnover above £44 million together with a balance sheet total above £38 million (regulation 2(1) of SI 2014/1643, as amended by SI 2023/1182).
Our is ESOS mandatory guide covers qualification in detail, and the Phase 4 thresholds guide covers the 31 December 2026 qualification date.
Action plan deadlines
For the third compliance period, the action plan deadline was 5 December 2024, six months after the extended Phase 3 notification deadline of 5 June 2024.
The plan had to be submitted through the MESOS digital service with board-level director sign-off.
The Environment Agency accepted action plans submitted after the deadline without remedial action until 5 March 2025.
That grace window has now closed — a Phase 3 participant that has still not submitted should engage the Environment Agency proactively rather than wait for enforcement contact.
| Obligation | Deadline | Status at August 2026 |
|---|---|---|
| Phase 3 compliance notification | 5 June 2024 | Passed |
| Action plan submission (reg 34A) | 5 December 2024 (accepted late until 5 March 2025) | Passed |
| First annual progress update (reg 34B) | 5 December 2025 | Passed |
| Second annual progress update (reg 34B) | 5 December 2026 | Upcoming |
| Phase 4 compliance notification | 5 December 2027 | Upcoming |
| Phase 4 action plan submission (reg 34A) | 5 December 2028 — covering 6 December 2027 to 5 December 2031 | Upcoming |
| Phase 4 first progress update (reg 34B) | 5 December 2029 | Upcoming |
| Phase 4 second progress update (reg 34B) | 5 December 2030 | Upcoming |
| Phase 4 third progress update (SI 2026/701 reg 28) | 5 December 2031 | Upcoming |
The deadlines above are set by SI 2014/1643 as amended and summarised in the GOV.UK ESOS guidance (updated 16 February 2026).
The Phase 4 notification deadline of 5 December 2027 is covered in our ESOS compliance guide.
Progress updates — two in Phase 3, three in Phase 4
Regulation 34B of SI 2014/1643 as amended requires progress updates against the action plan in the years following its submission.
For Phase 3 participants, those updates fall due on 5 December 2025 and 5 December 2026.
Phase 4 requires three progress updates rather than two.
Regulation 28 of the Energy Savings Opportunity Scheme (Amendment) Regulations 2026 (SI 2026/701) amends regulation 34B to add a final progress update for compliance periods ending on or after 5 December 2027.
The Phase 4 updates are therefore due on 5 December 2029, 5 December 2030 and 5 December 2031, per the Environment Agency Phase 4 guidance published 30 July 2026.
Each update reports what has actually been delivered against the commitments in the action plan.
Like the action plan itself, progress updates are submitted through MESOS and are made public (Sections 12–13, GOV.UK full guidance).
Board-level sign-off
The action plan must be signed off by a board-level director before submission (GOV.UK ESOS guidance).
This mirrors the board sign-off required for the ESOS assessment itself and puts the organisation's leadership formally behind the published commitments.
Because the commitments are public and will be tested in the Phase 4 assessment, boards should treat sign-off as more than a formality.
Over-committing creates a published record of unmet promises that must later be explained; under-committing is visible to stakeholders reviewing the published plan.
Submitting via MESOS
Action plans and progress updates are submitted through MESOS — the "Manage your ESOS reporting" digital service used for ESOS compliance notifications, operated by the Environment Agency as scheme administrator.
The Environment Agency published its ESOS Phase 4 guidance on 30 July 2026, confirming MESOS as the route for the Phase 4 notification of compliance, the action plan and every progress update.
The ESOS assessment, the action plan and each progress update must be signed off by one or more directors (or equivalent) before submission (EA ESOS Phase 4 guidance, §§ 12.1 and 14).
Phase 3 progress updates due on 5 December 2026 use the same service.
Public disclosure
Action plans and progress updates are made public (Sections 12–13, GOV.UK full guidance).
This is a deliberate design feature of the Part 6A framework: the audit stays internal, but the commitments and their delivery record do not.
Publication means customers, investors, and ESG due-diligence teams can compare what your organisation promised with what it reported delivering.
Organisations already preparing energy and emissions disclosure under SECR or UK SRS should align the narratives — an ESOS action plan that contradicts the annual report is an avoidable credibility risk.
What changes in Phase 4
The Environment Agency published the ESOS Phase 4 guidance on 30 July 2026.
It implements the Energy Savings Opportunity Scheme (Amendment) Regulations 2026 (SI 2026/701), made 23 June 2026, laid before Parliament 1 July 2026 and in force 22 July 2026.
Three duties are new, and two of them land directly on the action plan cycle.
First, the action plan review: the ESOS report and notification of compliance must identify the measures proposed in the previous action plan that were not implemented and explain why (EA ESOS Phase 4 guidance, summary of updates).
Those action plan review submissions are not published, although action plans and progress updates themselves are (EA ESOS Phase 4 guidance).
Second, achieved savings reporting: the report and notification must state the energy savings achieved during the compliance period — the measures implemented, the saving from each measure in kWh, and each measure's energy-saving category (EA ESOS Phase 4 guidance, summary of updates).
Only the combined saving across all measures is published; the per-measure figures are withheld as potentially commercially sensitive (EA ESOS Phase 4 guidance).
Third, a third progress update is added by regulation 28 of SI 2026/701, amending regulation 34B for compliance periods ending on or after 5 December 2027.
Phase 4 also removes Display Energy Certificates and Green Deal Assessments as compliance routes — regulation 26 of SI 2026/701 omits regulation 34 of the 2014 Regulations.
See the energy audit guide for the two surviving routes.
The net-zero refocus and the alignment of qualification thresholds with SECR remain postponed to Phase 5 (GOV.UK ESOS guidance).
For Phase 4 participants, the action plan cycle repeats after the 5 December 2027 notification deadline, with the Phase 4 action plan due by 5 December 2028.
That plan covers the period 6 December 2027 to 5 December 2031, and its progress updates fall due on 5 December 2029, 5 December 2030 and 5 December 2031 (EA ESOS Phase 4 guidance, § 14).
Penalties for non-compliance
Producing an action plan and its progress updates is a statutory obligation under Part 6A of SI 2014/1643 as amended, enforced by the Environment Agency (with equivalent regulators in the devolved nations).
No civil penalty attaches to missing either of them.
The Phase 4 guidance states that regulators "will not take enforcement action or issue a penalty relating to the non-submission of an action plan or progress update" (EA ESOS Phase 4 guidance, § 15.1).
The Scheme Administrator publishes the failure to submit instead — which for an organisation under investor or supply-chain ESG screening is the consequence that carries.
Penalties do apply elsewhere in the scheme: to failure to notify, failure to undertake the energy audit, failure to maintain records, failure to comply with a notice, and false or misleading statements.
The full penalty framework, including the fixed and daily penalty amounts, is set out in our ESOS penalties and enforcement guide.
Organisations behind on any action plan obligation should engage the Environment Agency proactively.
Early engagement and demonstrated good faith consistently produce better enforcement outcomes than waiting to be identified through the EA's compliance monitoring.
Frequently asked questions
What is the ESOS action plan deadline?
For Phase 3, participants who had to notify for the third compliance period were required to submit an action plan via the MESOS digital service by 5 December 2024.
The Environment Agency accepted action plans without remedial action until 5 March 2025.
Annual progress updates against the action plan are then due on 5 December 2025 and 5 December 2026.
Who must submit an ESOS action plan?
Every participant that was required to notify compliance for the third ESOS compliance period (Phase 3, notification deadline 5 June 2024) must submit an action plan.
The requirement was introduced by regulation 34A of SI 2014/1643, inserted by the ESOS (Amendment) Regulations 2023 (SI 2023/1182).
The plan must be signed off by a board-level director before submission.
How do I submit an ESOS action plan?
Action plans are submitted through MESOS — the "Manage your ESOS reporting" digital service operated by the Environment Agency as scheme administrator.
The same service is used for compliance notifications and for the progress updates.
The Environment Agency published its ESOS Phase 4 guidance on 30 July 2026, which confirms MESOS as the submission route for the Phase 4 notification of compliance, the action plan and every progress update, each requiring director (or equivalent) sign-off.
What is an ESOS progress report (progress update)?
A progress update is the report on delivery against the commitments in your ESOS action plan, required by regulation 34B of SI 2014/1643 as amended.
Phase 3 participants file two, on 5 December 2025 and 5 December 2026.
Phase 4 adds a third: SI 2026/701 regulation 28 requires a final progress update for compliance periods ending on or after 5 December 2027, so the Phase 4 updates fall due on 5 December 2029, 5 December 2030 and 5 December 2031.
Progress updates are made public, as is the action plan itself.
What happens to action plans in ESOS Phase 4?
The Environment Agency published the ESOS Phase 4 guidance on 30 July 2026, implementing the Energy Savings Opportunity Scheme (Amendment) Regulations 2026 (SI 2026/701), in force 22 July 2026.
The ESOS report and notification of compliance must now carry an action plan review identifying the measures proposed in the previous action plan that were not implemented, with reasons — and that submission is not published.
The report and notification must also state the energy savings actually achieved during the compliance period, measure by measure in kWh with each measure's energy-saving category, although only the combined figure across all measures is published.
A third progress update is added: the Phase 4 action plan is due 5 December 2028 and covers 6 December 2027 to 5 December 2031, with progress updates on 5 December 2029, 5 December 2030 and 5 December 2031.
Is an ESOS action plan mandatory, and what if we fail to submit?
Yes — the action plan and its progress updates are statutory obligations under Part 6A of SI 2014/1643 as amended.
But no civil penalty attaches to missing them.
The Environment Agency Phase 4 guidance states that regulators "will not take enforcement action or issue a penalty relating to the non-submission of an action plan or progress update"; the Scheme Administrator publishes the failure to submit instead.
Penalties do apply to the notification, the audit, record-keeping and false or misleading statements — see our ESOS penalties guide.
Authority sources
Continue reading
Related guides & references
ESOS Phase 4 Requirements & Thresholds
Qualification criteria at 31 December 2026, sterling thresholds, and the 5 December 2027 compliance deadline.
ESOS Energy Audit Requirements
The 95% coverage requirement, lead assessor rules, and audit content that feed the action plan.
ESOS Penalties and Enforcement
Civil sanctions framework, maximum penalties, and Environment Agency enforcement approach.
ISO 50001 as ESOS Compliance Route
How ISO 50001 certification interacts with ESOS obligations, including the action plan.